Rewa Ultra Mega Solar Limited (RUMSL), in collaboration with the Madhya Pradesh Power Transmission Company Limited (MPPTCL), has issued a turnkey tender for intra-state power evacuation infrastructure to connect Phase I of the 600 MW Morena Solar Park to the grid.

Key Infrastructure Deliverables

  • 400 kV Sabalgarh Substation: Construction of a high-voltage substation dedicated to power evacuation.

  • 400 kV Transmission Line: A double-circuit line linking Morena’s pooling facilities directly to the Sabalgarh substation.

  • 220 kV Line Works: Line-in-line-out (LILO) connections and network-strengthening modifications.

  • Pooling Substations: Two 33/220 kV pooling substations with integrated 220 kV transmission lines.

The project incorporates integrated Battery Energy Storage Systems (BESS) designed to supply peak-demand power. Synchronizing grid development directly with solar generation timelines mitigates curtailment risks, avoids grid congestion, and ensures seamless transmission to distribution companies across Madhya Pradesh.